Lewis Smith, Environment Editor
Grab an Italian masterpiece for less
Renewable energy and climate change targets for 2020 will be missed unless the National Grid speeds up the rate at which new generators are connected, leading industry figures have said.
The grid is undergoing its biggest upgrade since the 1960s as part of a £14 billion investment project by 2012 and up to £13.5 billion more by 2020.
Unless it is made easier, however, for renewable energy generators, particularly wind farms, to connect to the grid, the investment will fail to enable Britain to meet its 2020 targets. Under an EU agreement earlier this year, Britain committed itself to increasing its reliance on renewable energy from about 2 per cent to 15 per cent. To reach the target, up to 40 per cent of electricity will have to come from renewable sources, which will require a big programme to build wind farms.
Delays in linking new generators to the grid are already forcing projects to be postponed, and developers are being told they may have to wait until 2018 before they can be connected.
Planning rules are being reformed, and should be in force next year to help reduce the time it takes to get consent for generators and grid extensions, but few within the renewables industry believe that they will enable the 2020 targets to be reached.
William Law, chairman of Lunar Energy, which is developing tidal generators, described the state of the grid as the single biggest problem facing the renewables industry.
The upgrade of the grid over the next decade is expected to take into account the rise of renewable generators, which are usually situated in unpopulated parts of the country or at sea, and are therefore far removed from the existing infrastructure.
Among the improvements that are being worked on are connections between the English and Scottish grids, so that electricity from rich sources of renewable energy can get to places such as London where it is most needed.Gordon Edge, of the British Wind Energy Association, said: “There needs to be a wholesale change in how the system is managed. We need strong political direction and guidance – someone knocking heads together to make sure deadlines aren’t missed.”
Renewable Energy Systems, based in Kings Langley, Hertfordshire, has six wind farm projects that have been seriously delayed because it will take until at least 2016 before they can be connected to the grid. Richard Ford, its grid connections manager, was told that one of its wind farms proposed in Scotland could not be guaranteed a connection by 2018.
National Grid, which owns and manages the grid in England and Wales and oversees it in Scotland, is barred by the regulator, Ofgem, from investing in new transmission lines until developers with specific proposals and funding apply for connection.
Changing the remit of Ofgem, to allow National Grid to build the infrastructure before generators are built could halve the time it would take to get wind farms off the drawing board and into production. The idea has won support in the Lords, where an amendment to the Energy Bill, proposed by Lord Oxburgh, to widen the regulator’s role will be debated tomorrow.
Lord Jenkin of Roding said: “My main concern is to address the question of whether Ofgem should be taking account of social needs and climate change.”
Stewart Larque, of National Grid, singled out the planning system as the biggest barrier to rapid expansion but he agreed that the regulatory system needed to be changed. He said that there was an “unprecedented amount” of renewables planned that need to be linked to the grid.
Industry sectors news at a glance. Interactive heatmap, video and podcast
Everything the Business Traveller needs to know to make a better trip
Get ready for the winter sports season, with our resort guides and snow reports
We are backing British business, what is the confidence of the nation and what businesses are succeeding?
Growing demand for energy, oil that is harder to reach and the rise of carbon dioxide emissions. We examine the energy challenge
With rail travel in Europe on the rise, we review the benefits of travelling by train
Enjoy further reading from Travel to Fashion, Business to Sport, discover more
Shortcuts to help you find sections and articles
1998
£47,955
12 months for the price of 11 and a 5% discount.
Offer ends 31/11/09
Check your free Experian credit report before applying
Car Insurance
to £60K + bonus (OTE £90k)
Lord Search & Selection
Location Flexible
PwC’s Consulting practice helps businesses of all shapes
and sizes work smarter and grow faster.
£85k
CPA
Highly Competitve
Specsavers
Whiteley, near Southampton
Moments from Battersea Park.
For sale with Winkworth
Find out about shared ownership.
See your free Experian credit report beforehand
Book now & save over £100pp.
11 cool resorts, lowest prices... Early Booking offers 15 Nov.
20% off selected Azores holidays taken in October with Sunvil Discovery
Get covered on your travels with a superb range of policies at great prices. Visit InsureandGo.com
World Class Golf, Spa and preferential Beach Club. Private estate overlooking West Coast
Villas from £275 per night inclusive of Golf
Contact our advertising team for advertising and sponsorship in Times Online, The Times and The Sunday Times, or place your advertisement.
Times Online Services: Dating | Jobs | Property Search | Used Cars | Holidays | Births, Marriages, Deaths | Subscriptions | E-paper
News International associated websites: Globrix Property Search | Milkround
Copyright 2009 Times Newspapers Ltd.
This service is provided on Times Newspapers' standard Terms and Conditions. Please read our Privacy Policy.To inquire about a licence to reproduce material from Times Online, The Times or The Sunday Times, click here.This website is published by a member of the News International Group. News International Limited, 1 Virginia St, London E98 1XY, is the holding company for the News International group and is registered in England No 81701. VAT number GB 243 8054 69.